Step 3: Sprint Planning (Requirements)

If you’ve followed the first 2 steps in this series, you should now have your product backlog in order and have estimated its size using Fibonacci points.

The next step – Step #3 – is to plan your Sprint.

Sprint Planning Workshop

Call a Sprint Planning meeting. Make sure the meeting is attended by the whole team. Include all roles. Business Analysts if you have them. Testers if you have them. ALL Developers on the Scrum team for the product. And very importantly the Product Owner.

The first thing you must do (in your first Sprint Planning meeting) is decide on your Sprint duration. This decision should be taken as a team.

Decide Your Sprint Duration

This is an important decision. Scrum suggests 30 days. It might be right. But this is one point that seems to be widely adapted by agile teams practicing Scrum.

The optimum Sprint duration depends on many factors. Something I read recently suggested that a development team’s ‘cycle time’ is a direct reflection of the maturity of their processes. I think I would agree with that statement.

A team with immature processes will find the intensity of Scrum and the overhead of Sprint Planning, Testing, Deployment and Review quite onerous for a short Sprint cycle. Whereas teams with very mature processes (for example automated testing, automated deployment, and teams who’ve become very quick at Sprint Planning), a short cycle might be very comfortable.

I’d suggest the range is between 1 week and 1 month. 1 week is probably the shortest that will ever be practical, although if you really master agile practices, why not ship each new feature when it’s ready? (if that’s appropriate for the product). 1 month should certainly be the longest.

For fast-moving products or markets, such as web-based products – where there is central deployment and no rollout or user training – 1 month seems like a lifetime! Personally I like 2 week Sprints for fast moving products.

Mike Cohn is one of the key exponents of agile development. See here for Mike’s article giving further advice about how to select the optimum iteration length.

Keep Sprint Duration Consistent

Whatever Sprint duration you choose to go for, my advice is to keep it consistent.

This, in fact, is more important than the length itself. Because it’s this consistency that allows you to get into a rythm. It’s this consistency that makes your process very repeatable. And therefore helps you to get into your stride as a team. And it’s this consistency that allows you to start understanding how many Product Backlog points you can typically do in a Sprint.

Once you’ve decided, you can now set up a Sprint Planning Workshop as a recurring appointment before every Sprint.

Select Target Backlog for Sprint

Now you’ve decided on your Sprint duration. Next you must decide on the goal for the Sprint…

Looking at the top section of the Product Backlog, what would seem to be a reasonable goal to set for the Sprint? Can you express an objective that sums up the goal for the next Sprint, or at least pick a section of items/features from the top of the Product Backlog that the team thinks can be achieved in the Sprint duration?

Select your target backlog for the Sprint. Make this decision as a team.

Include a bit more than you think can be achieved. It’s important to prepare more items during planning in case the team finishes early. These items can be clearly identified as stretch tasks and the Product Owner should not expect them to be completed. These are the things you will only do if the Sprint goes better than you expected.

In future Sprints, you will be able to use your Scrum team’s previous Velocity to help with this decision. Velocity is the number of Product Backlog Points delivered in a Sprint. This tends to fluctuate wildly early on when adopting Scrum. But it will settle down as the team get into a rythm, and in future provide you with a reasonable norm to base your target backlog on.

Clarify Sprint Requirements

Take each item on the Product Backlog. It’s important to go through them methodically, one item at a time…

The Product Owner presents each item and explains how he/she sees it working from a functional perspective.

The whole team discusses the item in detail. The whole team asks questions about the feature in order to establish what it should do and how it should work.

The outcomes of this discussion should be captured on a whiteboard or flipchart, or someone could write notes on a laptop as the discussion progresses. Interactive or printable whiteboards are ideal for this process.

You can use whatever form of writing requirements you want to. But the important principle in Scrum, and in any agile development methodology, is that you write requirements feature by feature, just before they are developed.

Write requirements in a way that is lightweight and visual. Agile requirements should be barely sufficient. The fact the features will be developed and tested within the next few weeks, and by the team that were present, makes this possible.

Consider writing ‘User Stories’, a concept from XP (Extreme Programming). It’s beyond the scope of this article to explain user stories in any detail. But the basic concept is to write features using this construct:

As a [type of user], I want to [do whatever], so I can [achieve what goal].

The story can be backed up by a sketch of the UI, a wireframe or visuals. Annotate the sketch to describe the functionality. Backed it up with statements about how it will be confirmed (or tested). This will help to identify scenarios up front, before it’s developed.

For more information about user stories, Mike Cohn has written a book, User Stories Applied.

Next…

Once you have clarified the requirements for all the Product Backlog items targeted for your Sprint, the next step is Step #4: Sprint Planning/estimate tasks

Kelly.

See also:

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent Posts

In The Zone with Marcin Zasepa

Welcome to the second in our new series, ‘in the zone’, a collection of conversations with CTO’s within the CTO Zone community. Each week we’ll be discussing the latest trends, insights gained from there experiences, and future predictions for their industry. This week we’d like to welcome Marcin Zasepa, CTO at Homegate AG in Switzerland. Every episode will be approximately 30 minutes

Read More »

In The Zone with Sasha Bilton

Welcome to the first in our new series, ‘in the zone’, a collection of conversations with CTO’s within the CTO Zone community. Each week we’ll be discussing the latest trends, insights gained from there experiences, and future predictions for their industry. This week we’d like to welcome Sasha Bilton. Every episode will be approximately 30 minutes long, and we aim

Read More »

Case Study: DAZN Data Engineering

Find out how 101 Ways helped DAZN improve their existing data warehouse as well as planning and setting the foundations of the new cloud-based data platform. Click here to download the full case study. Get in touch with a member of the 101 Ways team if you would like to discuss ways in which we can help you and your company

Read More »

Search the Blog

Agile Management Made Easy!

All About Agile

By Kelly Waters

“’Agile’ is one of the biggest buzzwords of the last decade. Agile methods often come across as rather more complicated than they really are. This book is an attempt to unravel that complexity. To simplify the concepts. This book breaks the concepts into small bite-sized pieces that are easy to understand and easy to implement and delivers the message in a friendly and conversational style. Allaboutagile.com is one of the most popular blogs about agile on the web. ”

Kelly Waters

Agile 101 is available to purchase. GAME ON!

Agile 101

Emma Hopkinson-Spark

“Whilst there are lots of ways you can vary the game depending on the teams you have and the learning outcomes you want, the basic flow of the game play is common to all.”
Emma Hopkinson-Spark

Why did we make the game?

How to play the game?

London

101 Ways Limited
41 Corsham Street
London
N1 6DR
United Kingdom

Manchester

101 Ways Limited
No.1 Spinningfields
Quay Street
Manchester
M3 3JE
United Kingdom

Amsterdam

101 Ways BV
Weesperstraat 61-105
1018 VN Amsterdam
Netherlands

Contact Us

If you would like to get in touch with one of the team at 101 Ways, then please fill out the form below or email us at contact-us@101ways.com.