A software release may result from multiple iterations (or ‘Sprints’ in Scrum).

Sprint Planning is about planning what’s included in the next iteration.

Whereas Release Planning is about planning multiple Sprints, in order to predict when a release (or releases) might be delivered.

Release Planning is a very simple way of doing some top-down planning. Much less complex than a more traditional project plan on a Gantt-chart. Therefore much quicker to do. And, I would say, no more or less accurate.

First of all, let’s assume you already have your Product Backlog (feature list), with all your User Stories set out in priority order. Let’s also assume that you’ve estimated your product backlog, ideally using Story Points.

If you already have an established team doing Scrum or XP (eXtreme Programming), use the team’s known Velocity to divide the Product Backlog into Sprints.

However, if the team is not already using Scrum or XP, you need to estimate the team’s Velocity. To do this, you must first make an assumption about the team size that is likely for the release. Then, you need to decide on your Sprint duration and, ideally with the input of the team, decide how many of the initial User Stories you think could reasonably be achieved in a Sprint. Add up the Story Points for these items. Using this number of Story Points as the team’s estimated Velocity, divide the Product Backlog into Sprints.

If the project team is not already established, add a ‘Sprint Zero’ at the beginning to get things ready for the first Sprint, for instance getting the team organised, briefing meetings, setting up development and test environments, preparing the first set of User Stories, etc.

If it’s a large or complex release, add a ‘Stabilisation Sprint’ (or more than one Sprint if appropriate) at the end to stabilise the release. By this, for instance, I mean stop adding new features, complete regression testing, bring the defect count down to an acceptable level, prepare for deployment, etc.

If the predicted end date is not acceptable for the project’s objectives, alter the assumption about the team size (and associated costs!) and re-calculate.

And there you have it! A Release Plan that provides an outline of the Sprints, what’s included in each, and an estimated date for the release.

Kelly.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent Posts

Six Actionable Nuggets of Advice for Becoming a First-time Technology NED

If the pandemic has taught companies anything it’s that tech is not something that you put off and think about ‘later’. The last year has seen organisations go through huge digital transformations, whether planned or otherwise. And for those that aren’t technology-based companies, getting the right board-level advice can not only be hard to find, but the difference between success

Read More »

Culture, Skills, and Capabilities // How to become a more data-driven organisation

In our whitepaper “How to become a more data-driven organisation”, we wrote about the five steps that an organisation would need to take, which are: Outcomes: Defining goals and metrics to ensure clear and measurable outcomes Analytics: Implementing and sharing the analytics to improve data-driven decision making Innovation: Testing assumptions through hypothesis testing and learning Data Platform: Gaining new insights

Read More »

Data Platform // How to become a more data-driven organisation

This is the fourth article in our series on “How to become a more data-driven organisation”, and we are going to be focusing on Data Platforms. It is at this point that most people start to dive deep into the technical aspects of Data Lakes vs Data Warehouses, but we want to bring us back up a level and ask

Read More »

Search the Blog

Agile Management Made Easy!

All About Agile

By Kelly Waters

“’Agile’ is one of the biggest buzzwords of the last decade. Agile methods often come across as rather more complicated than they really are. This book is an attempt to unravel that complexity. To simplify the concepts. This book breaks the concepts into small bite-sized pieces that are easy to understand and easy to implement and delivers the message in a friendly and conversational style. Allaboutagile.com is one of the most popular blogs about agile on the web. ”

Kelly Waters

Agile 101 is available to purchase. GAME ON!

Agile 101

Emma Hopkinson-Spark

“Whilst there are lots of ways you can vary the game depending on the teams you have and the learning outcomes you want, the basic flow of the game play is common to all.”
Emma Hopkinson-Spark

Why did we make the game?

How to play the game?

London

101 Ways Limited
145 City Rd
London
EC1V 1AZ
United Kingdom

Amsterdam

101 Ways BV
Weesperstraat 61-105
1018 VN Amsterdam
Netherlands

Contact Us

If you would like to get in touch with one of the team at 101 Ways, then please fill out the form below or email us at contact-us@101ways.com.